uGrind: Machine Installation

Installation Procedure

1. Safety Rules
Before placing the machine on the production floor, make sure that the ground is thick and strong enough to endure mechanical vibration and support the weight of the machine for a long time.

2. Lifting the Machine
Use lifting equipment with sufficient strength such as a crane, forklift, wire ropes and hooks. Pay special attention to the balance of the machine while lifting.

3. Leveling Spacers
The provided toolbox includes four adjustable leveling spacers with screws. The four spacers must be properly adjusted to ensure machine stability.

4. Machine Positioning
The floor where the machine is going to be installed must be absolutely flat and leveled. It is important to position the machine prior assembling its optional equipment such as loading and unloading systems.

5. Machine Leveling
After positioning, use high precision level gauges to correctly calibrate the machine and make sure it is perfectly leveled.